Marburg reliability improvement project $310,000

On behalf of Russell Howard, Asset Manager Western Region, please be advised Energex will commence upgrading parts of the overhead electricity network in Marburg over the next few weeks. These works will help ensure a more reliable and secure electricity supply for the region. Work is expected to commence early April and we anticipate completion by the end of June 2012. 
Please contact Shaun Rushby, Project Coordinator on (07) 3664 6627, should you require further information or clarification about this project.
As part of our commitment to a safe and reliable power supply, Energex will commence upgrading parts of the existing overhead electricity network in Marburg over the next few weeks.
This project involves reinforcing the overhead network that currently supplies electricity to customers in Marburg, Tallegalla, Haigslea, Glamorgan Vale, Mount Marrow and Walloon areas.
Works include the installation of new electrical equipment and pole replacements in the following areas:
∙ Warrego Highway (near Telrader Road)
∙ Linnings Road
∙ Claus Road
∙ Butlers Road
∙ Thagoona Haigslea Road
∙ Haigslea Malabar Road
* Rosewood Marburg Road
* Taylors Road
Crews will commence work early May and once complete, this project will allow us to identify network issues and provide quicker restoration times if unexpected interruptions occur.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: