Kerners Road Deviation Project – dates of Service Relocation Works

Advice of upcoming service relocation works at Warwick Rd (at the intersection of Hall St) as part of the Kerner’s Rd Deviation Project. The following times are indicative and subject to change due to weather and other unforseen delays -:

TELSTRA – start on the 15th of June (in the coming week) and finish mid-August
ENERGEX – temporary works (pole/light relocations) are scheduled to start in July and finish at the start of September
OPTUS – to follow Energex with completion mid-September.

Council is negotiating with Ipswich Water who will be carrying out the water main installations, as completion of these is required before our crews can begin road works. Should Main Roads give there approval to these designs and we reach an agreement with Ipswich Water, it is possible that these works may begin as early as August 2010.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: